Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-14-06 07-2W6904 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 52% Location: Federal Project: 07-LA-5-13.8/28.2 NONE Progress payment No. 007 Payment period ending: 08-20-16 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 556,744.35 82,323.80 2. a. Extra Work 37,289.62 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 594,033.97 82,323.80 5. Mobilization 70,000.00 0.00 6. Total Work Completed 664,033.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 664,033.97 82,323.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,323.80