Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-13-12 07-2W7004 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 51% Location: Federal Project: 07-LA-10-0.0 NHP-X037(176) Progress payment No. 002 Payment period ending: 12-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 60,060.80 49,310.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 60,060.80 49,310.80 5. Mobilization 29,500.00 29,500.00 6. Total Work Completed 89,560.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 89,560.80 78,810.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,810.80