Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-11-44 07-2W7004 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 55% Location: Federal Project: 07-LA-10-0.0 NHP-X037(176) Progress payment No. 008 Payment period ending: 06-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 835,539.53 115,920.00 2. a. Extra Work 187.93 187.93 b. Adustment Comp. 4,178.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 839,906.36 116,107.93 5. Mobilization 59,000.00 0.00 6. Total Work Completed 898,906.36 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 898,906.36 116,107.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,107.93