Dept. of Trans. PROGRESS Serial No. Contract No. 16-116-07-57 07-2W7104 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 59% Location: Federal Project: 07-VEN-33-0.0 NONE Progress payment No. 001 Payment period ending: 04-20-16 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,200.00 10,200.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,200.00 10,200.00 5. Mobilization 6. Total Work Completed 10,200.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,200.00 10,200.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,200.00