Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-14-32 07-2W7104 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 68% Location: Federal Project: 07-VEN-33-0.0 NONE Progress payment No. 002 Payment period ending: 05-20-16 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 410,847.40 400,647.40 2. a. Extra Work b. Adustment Comp. 105,868.00 105,868.00 3. Materials on Hand 4. Earned Subject to Retention 516,715.40 506,515.40 5. Mobilization 95,000.00 95,000.00 6. Total Work Completed 611,715.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 611,715.40 601,515.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 601,515.40