Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 15-334-15-35 07-2W7304 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 35% Location: Federal Project: 07-LA-110-7.0/16.7 NHPI-110-1(825) Progress payment No. 003 Payment period ending: 11-20-15 AUTOBAHN CONSTRUCTION INC. 933 N. BATAVIA ST. ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 268,861.74 45,230.88 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 268,861.74 45,230.88 5. Mobilization 85,500.00 0.00 6. Total Work Completed 354,361.74 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 354,361.74 45,230.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,230.88