Dept. of Trans. PROGRESS Serial No. Contract No. 16-025-14-56 07-2W7304 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 50% Location: Federal Project: 07-LA-110-7.0/16.7 NHPI-110-1(825) Progress payment No. 005 Payment period ending: 01-20-16 AUTOBAHN CONSTRUCTION INC. 933 N. BATAVIA ST. ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 599,461.52 90,997.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 599,461.52 90,997.50 5. Mobilization 90,000.00 0.00 6. Total Work Completed 689,461.52 7. Deductions -14,000.00 -11,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 675,461.52 79,997.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,997.50