Dept. of Trans. PROGRESS Serial No. Contract No. 15-296-09-11 07-2W8304 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 5% Location: Federal Project: 07-LA-2-26.4/82.3 STP-P002(38) Progress payment No. 001 Payment period ending: 10-20-15 INTERMOUNTAIN SLURRY SEAL, INC. 1005 TERMINAL WAY STE. 220 RENO NV 89502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,090.88 261,090.88 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 261,090.88 261,090.88 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 336,090.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 336,090.88 336,090.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 336,090.88