Dept. of Trans. PROGRESS Serial No. Contract No. 15-327-10-55 07-2W8404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 92% Location: Federal Project: 07-LA-101-27.6/32.1 NONE Progress payment No. 006 Payment period ending: 11-20-15 VELARDE CONCRETE CONSTRUCTION, INC. 523 S BRAND BLVD STE 201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 524,584.80 5,202.50 2. a. Extra Work 109,017.52 0.00 b. Adustment Comp. -385.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 633,217.32 5,202.50 5. Mobilization 25,000.00 0.00 6. Total Work Completed 658,217.32 7. Deductions -35,155.30 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 623,062.02 5,202.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,202.50