Dept. of Trans. PROGRESS Serial No. Contract No. 20-055-16-37 07-2W9404 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 81% Location: Federal Project: 07-LA-710-17.3/26.3 NONE Progress payment No. 010 Payment period ending: 02-20-20 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 764,916.48 8,694.96 2. a. Extra Work 122,074.29 60,390.29 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 886,990.77 69,085.25 5. Mobilization 51,783.93 0.00 6. Total Work Completed 938,774.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 938,774.70 69,085.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,085.25