Dept. of Trans. PROGRESS Serial No. Contract No. 16-299-16-08 07-2W9504 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 63% Location: Federal Project: 07-LA-10-31.1/42.5 NONE Progress payment No. 003 Payment period ending: 10-20-16 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 322,919.88 250,200.73 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 322,919.88 250,200.73 5. Mobilization 50,000.00 12,500.00 6. Total Work Completed 372,919.88 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 368,919.88 258,700.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 258,700.73