Dept. of Trans. PROGRESS Serial No. Contract No. 16-328-13-16 07-2W9604 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 97% Location: Federal Project: 07-LA-60-11.3/R23.3 NONE Progress payment No. 005 Payment period ending: 11-20-16 WESTERN STRUCTURES 6005 TYLER ST RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 649,241.50 114,947.01 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 649,241.50 114,947.01 5. Mobilization 68,882.96 0.00 6. Total Work Completed 718,124.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 718,124.46 114,947.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,947.01