Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-209-11-01 07-2X1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-47-3.5/4.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-22-09 GRIFFITH COMPANY 12631 E. IMPERIAL HWY.STEF230 SANTA FE SPRINGS, CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,614.00 0.00 2.a. Extra Work 319,249.19 35,313.41 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 321,863.19 35,313.41 5. Mobilization 6. Total Work Completed 321,863.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 321,863.19 35,313.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,313.41