Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-248-14-47 07-2X2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-110-31.2 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-19-08 BALTAZAR CONSTRUCTION, INC. 236 E. ARROW HWY COVINA, CA 91722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,448.00 2,448.00 2.a. Extra Work 130,977.80 130,977.80 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 133,425.80 133,425.80 5. Mobilization 6. Total Work Completed 133,425.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 133,425.80 133,425.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,425.80