Dept. of Trans. PROGRESS Serial No. Contract No. 11-297-13-24 07-2X3704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 6% 07-LA-14-29.3/31.0 Federal Project: ACST-45J1(4) P-45J1(4) Progress payment No. 01 Payment period ending: 10-20-11 SULLY-MILLER CONTRACTING COMPANY 135 S STATE COLLEGE BLVD BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,792.57 38,792.57 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 38,792.57 38,792.57 5. Mobilization 6. Total Work Completed 38,792.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 38,792.57 38,792.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,792.57