Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-244-16-53 07-2X7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-110-13.7 Federal Project: 07-LA-105-7.4 NONE Progress payment No. 05 Payment period ending: 07-28-10 ORTIZ ENTERPRISES, INC. 6 CUSHING, SUITE 200 IRVINE CA 92618-4221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,130.00 0.00 2.a. Extra Work 389,348.40 90,358.11 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 394,478.40 90,358.11 5. Mobilization 6. Total Work Completed 394,478.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 394,478.40 90,358.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,358.11