Dept. of Trans. PROGRESS Serial No. Contract No. 11-220-11-50 07-2X8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 46% 07-VEN-33-55.0/57.5 Federal Project: 07-VEN-33-0.0 NONE Progress payment No. 03 Payment period ending: 08-06-11 SUMMER CONSTRUCTION, IN.C 15245 TELEGRAPH ROAD SANTA PAULA, CA 93060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 590,344.87 153,329.32 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 590,344.87 153,329.32 5. Mobilization 6. Total Work Completed 590,344.87 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 590,344.87 153,329.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 153,329.32