Dept. of Trans. PROGRESS Serial No. Contract No. 23-116-15-38 07-2XC804 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 100% Location: Federal Project: 07-LA-5-20.6/21.4 NONE Progress payment No. 001 Payment period ending: 04-20-23 PTM GENERAL ENGINEERING SERVICES INC 5942 ACORN ST RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 58,440.24 58,440.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 58,440.24 58,440.24 5. Mobilization 6. Total Work Completed 58,440.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,440.24 58,440.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,440.24