Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-15-43 07-2XG804 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 83% Location: Federal Project: 07-LA-1-352.0/44.1 NONE Progress payment No. 007 Payment period ending: 05-20-24 DRILL TECH DRILLING & SHORING DBA APEX ROCKFALL MITIGATION 2200 WYMORE WAY ANTIOCH CA 94509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 625,352.65 21,439.57 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 625,352.65 21,439.57 5. Mobilization 6. Total Work Completed 625,352.65 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 615,352.65 11,439.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,439.57