Dept. of Trans. PROGRESS Serial No. Contract No. 24-236-16-32 07-2XH304 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 57% Location: Federal Project: 07-LA-118-11.6/11.6 NONE Progress payment No. 004 Payment period ending: 08-20-24 HARTFIELD CONSTRUCTION CORP 11908 CLARK ST UNIT A ARCADIA CA 91006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 159,425.37 62,041.78 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 159,425.37 62,041.78 5. Mobilization 6. Total Work Completed 159,425.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 159,425.37 62,041.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,041.78