Dept. of Trans. PROGRESS Serial No. Contract No. 24-346-14-43 07-2XJ404 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 07-VEN-34-8.9/8.9 NONE Progress payment No. 007 Payment period ending: 12-06-24 BALTAZAR CONSTRUCTION, INC 236 E. ARROW HWY COVINA CA 91722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 391,805.61 27,021.79 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 391,805.61 27,021.79 5. Mobilization 6. Total Work Completed 391,805.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 391,805.61 27,021.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,021.79