Dept. of Trans. PROGRESS Serial No. Contract No. 24-346-14-19 07-2XK004 PROGRESS PAYMENT VOUCHER %complete: %time: 6% 38% Location: Federal Project: 07-LA-23-0.0 NONE 07-VEN-23 Progress payment No. 002 Payment period ending: 12-06-24 SUMMER CONSTRUCTION INC PO BOX 30 SANTA PAULA CA 93061 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 152,681.80 127,069.76 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 152,681.80 127,069.76 5. Mobilization 6. Total Work Completed 152,681.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 152,681.80 127,069.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 127,069.76