Dept. of Trans. PROGRESS Serial No. Contract No. 24-171-08-50 07-2XK704 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 65% Location: Federal Project: 07-LA-10-15.6/17.6 NONE Progress payment No. 004 Payment period ending: 06-20-24 AZ CONSTRUCTION INC 727 GLENDORA AVE LA PUENTE CA 91744 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 793,449.59 300,339.32 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 793,449.59 300,339.32 5. Mobilization 6. Total Work Completed 793,449.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 793,449.59 300,339.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 300,339.32