Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-16-22 07-2XM204 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 37% Location: Federal Project: 07-LA-1-1.4/7.3 NONE Progress payment No. 003 Payment period ending: 05-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 998,252.40 90,312.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 998,252.40 90,312.95 5. Mobilization 6. Total Work Completed 998,252.40 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 988,252.40 80,312.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 80,312.95