Dept. of Trans. PROGRESS Serial No. Contract No. 24-262-14-34 07-2XM604 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 100% Location: Federal Project: 07-VEN-101-40.0/40.4 NONE Progress payment No. 007 Payment period ending: 09-20-24 SUMMER CONSTRUCTION INC PO BOX 30 SANTA PAULA CA 93061 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 714,460.22 185,051.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 714,460.22 185,051.97 5. Mobilization 6. Total Work Completed 714,460.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 714,460.22 185,051.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 185,051.97