Dept. of Trans. FINAL Serial No. Contract No. 25-192-10-17 07-2XN604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-VEN-150-6.1/6.3 NONE Progress payment No. 004 Payment period ending: 08-20-24 R&R PIPELINE INCORPORATED 1315 E MAIN ST SANTA PAULA CA 93060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,628.00 0.00 2. a. Extra Work 325,255.88 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 341,883.88 0.00 5. Mobilization 6. Total Work Completed 341,883.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 341,883.88 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00