Dept. of Trans. PROGRESS Serial No. Contract No. 26-026-09-53 07-2XR304 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 66% Location: Federal Project: 07-LA-27-0.0/11.0 NONE Progress payment No. 011 Payment period ending: 01-20-26 FLO ENGINEERING INC 902 S VANHORN AVE WEST COVINA CA 91790 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 12,024,367.62 192,662.23 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,024,367.62 192,662.23 5. Mobilization 6. Total Work Completed 12,024,367.62 7. Deductions -30,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,994,367.62 212,662.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 212,662.23