Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-16-23 07-2XS204 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 520% Location: Federal Project: 07-LA-1-37.0/46.0 NONE Progress payment No. 004 Payment period ending: 07-20-25 C A RASMUSSEN INC 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 974,814.71 147,266.12 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 974,814.71 147,266.12 5. Mobilization 6. Total Work Completed 974,814.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 974,814.71 147,266.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,266.12