Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-032-13-36 07-2Y0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-60-0.5/0.7 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-08-07 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 537,514.55 26,447.76 2.a. Extra Work 30,232.78 30,232.78 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 567,747.33 56,680.54 5. Mobilization 55,000.00 0.00 6. Total Work Completed 622,747.33 7. Deductions 0.00 57,600.00 8. a.Contract Retentions -25,553.34 0.00 b. Unsatisfactory Prog. 0.00 6,273.89 c. Reduction after 95% Comp. 25,553.34 25,553.34 9. Total pay to Contractor 622,747.33 146,107.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 146,107.77