Dept. of Trans. PROGRESS Serial No. Contract No. 08-358-13-24 07-2Y5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 07-LA-1-9.5/12.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 12-20-08 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 02384 Total Estimate This Estimate 1. Contract Itms Without Mobil. 955,538.63 115,570.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 955,538.63 115,570.29 5. Mobilization 10,800.00 0.00 6. Total Work Completed 966,338.63 7. Deductions -78,400.00 0.00 8. a.Contract Retentions -47,776.93 -5,778.51 b. Unsatisfactory Prog. -45,174.54 -5,778.51 c. Reduction after 95% Comp. 9. Total pay to Contractor 794,987.16 104,013.27 10. Reduction Amt to Escrow 11. Payment to Escrow 47,770.00 12. Net Pymt. this Estimate 104,013.27