Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-070-11-09 07-2Y5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-47-L0.0/R2.4 Federal Project: NONE Progress payment No. 08 Payment period ending: 12-22-08 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 02383 Total Estimate This Estimate 1. Contract Itms Without Mobil. 612,387.52 0.00 2.a. Extra Work b. Adjustment Comp. -32,914.00 -32,914.00 3. Materials on Hand 4. Earned Subject to Retention 579,473.52 -32,914.00 5. Mobilization 24,000.00 0.00 6. Total Work Completed 603,473.52 7. Deductions -12,600.00 0.00 8. a.Contract Retentions -30,181.03 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 30,181.03 0.00 9. Total pay to Contractor 590,873.52 -32,914.00 10. Reduction Amt to Escrow -30,180.00 0.00 11. Payment to Escrow 30,180.00 12. Net Pymt. this Estimate -32,914.00