Dept. of Trans. PROGRESS Serial No. Contract No. 09-204-08-33 07-2Y7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 39% 07-LA-10-29.4/42.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-09 CAROLINO CONSTRUCTION CORPORATION 3035 EAST 8TH STREET NATIONAL CITY CA 91950 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 344,506.13 149,513.61 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 344,506.13 149,513.61 5. Mobilization 15,000.00 750.00 6. Total Work Completed 359,506.13 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 359,506.13 150,263.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150,263.61