Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-11-19 07-2Y8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 63% 07-LA-134-R6.1/R13.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-08 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 02316 Total Estimate This Estimate 1. Contract Itms Without Mobil. 516,480.50 53,997.00 2.a. Extra Work 53,930.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 570,410.50 53,997.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 590,410.50 7. Deductions 8. a.Contract Retentions -28,520.53 -2,699.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 561,889.97 51,297.15 10. Reduction Amt to Escrow 11. Payment to Escrow 28,520.00 12. Net Pymt. this Estimate 51,297.15