Dept. of Trans. PROGRESS Serial No. Contract No. 19-168-13-06 07-300404 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 37% Location: Federal Project: 07-LA-101-1.5/29.1 ACNH-Q101(332) Progress payment No. 014 Payment period ending: 06-20-19 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,524,815.15 882,239.50 2. a. Extra Work 263,730.35 1,714.71 b. Adustment Comp. 8.00 0.00 3. Materials on Hand 183,357.53 0.00 4. Earned Subject to Retention 8,971,911.03 883,954.21 5. Mobilization 1,215,000.00 0.00 6. Total Work Completed 10,003,553.50 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,181,911.03 883,954.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 883,954.21