Dept. of Trans. PROGRESS Serial No. Contract No. 20-055-15-12 07-300404 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 91% Location: Federal Project: 07-LA-101-1.5/29.1 ACNH-Q101(332) Progress payment No. 022 Payment period ending: 02-20-20 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,003,188.55 253,712.00 2. a. Extra Work 735,249.60 96,235.05 b. Adustment Comp. 27,645.19 0.00 3. Materials on Hand 167,357.53 -51,000.00 4. Earned Subject to Retention 11,933,440.87 298,947.05 5. Mobilization 1,215,000.00 0.00 6. Total Work Completed 12,981,083.34 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,143,440.87 298,947.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 298,947.05