Dept. of Trans. PROGRESS Serial No. Contract No. 18-331-09-40 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 24% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 004 Payment period ending: 11-20-18 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,702,416.66 2,516,512.99 2. a. Extra Work 33,896.07 33,896.07 b. Adustment Comp. 3. Materials on Hand 116,525.49 -25,737.03 4. Earned Subject to Retention 4,852,838.22 2,524,672.03 5. Mobilization 622,012.50 207,337.50 6. Total Work Completed 5,358,325.23 7. Deductions 0.00 9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,474,850.72 2,741,009.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,741,009.53