Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-10-19 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 32% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 006 Payment period ending: 01-20-19 ALL AMERICAN ASPHALT REFUND PAYMENT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,555,781.91 709,803.34 2. a. Extra Work 55,981.03 0.00 b. Adustment Comp. 3. Materials on Hand 203,557.97 3,804.09 4. Earned Subject to Retention 6,815,320.91 713,607.43 5. Mobilization 787,882.50 0.00 6. Total Work Completed 7,399,645.44 7. Deductions -10,000.00 285,890.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,593,203.41 999,497.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 999,497.43