Dept. of Trans. PROGRESS Serial No. Contract No. 19-114-10-21 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 26% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 009 Payment period ending: 04-20-19 ALL AMERICAN ASPHALT REFUND PAYMENT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,283,720.80 1,877,624.42 2. a. Extra Work 121,526.28 0.00 b. Adustment Comp. 3. Materials on Hand 366,488.47 127,964.47 4. Earned Subject to Retention 10,771,735.55 2,005,588.89 5. Mobilization 787,882.50 0.00 6. Total Work Completed 11,193,129.58 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,554,618.05 2,000,588.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,000,588.89