Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-11-55 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 28% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 010 Payment period ending: 05-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,713,200.98 1,429,480.18 2. a. Extra Work 121,526.28 0.00 b. Adustment Comp. 3. Materials on Hand 479,527.54 113,039.07 4. Earned Subject to Retention 12,314,254.80 1,542,519.25 5. Mobilization 787,882.50 0.00 6. Total Work Completed 12,622,609.76 7. Deductions -11,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,091,137.30 1,536,519.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,536,519.25