Dept. of Trans. PROGRESS Serial No. Contract No. 19-170-15-33 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 34% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 011 Payment period ending: 06-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,866,373.32 1,153,172.35 2. a. Extra Work 121,526.28 0.00 b. Adustment Comp. 3. Materials on Hand 392,273.69 -87,253.85 4. Earned Subject to Retention 13,380,173.29 1,065,918.50 5. Mobilization 787,882.50 0.00 6. Total Work Completed 13,775,782.10 7. Deductions -5,000.00 6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,163,055.79 1,071,918.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,071,918.50