Dept. of Trans. PROGRESS Serial No. Contract No. 19-203-18-41 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 39% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 012 Payment period ending: 07-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,408,362.02 2,541,988.72 2. a. Extra Work 176,620.54 55,094.26 b. Adustment Comp. 3. Materials on Hand 277,427.10 -114,846.59 4. Earned Subject to Retention 15,862,409.66 2,482,236.39 5. Mobilization 829,350.00 41,467.50 6. Total Work Completed 16,414,332.56 7. Deductions -9,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,682,759.66 2,519,703.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,519,703.89