Dept. of Trans. PROGRESS Serial No. Contract No. 19-263-13-53 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 46% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 014 Payment period ending: 09-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,275,459.15 1,780,183.09 2. a. Extra Work 416,798.67 168,493.86 b. Adustment Comp. 3. Materials on Hand 129,859.86 -80,104.00 4. Earned Subject to Retention 20,822,117.68 1,868,572.95 5. Mobilization 829,350.00 0.00 6. Total Work Completed 21,521,607.82 7. Deductions -52,000.00 -43,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,599,467.68 1,825,572.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,825,572.95