Dept. of Trans. PROGRESS Serial No. Contract No. 19-294-16-27 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 51% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 015 Payment period ending: 10-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,653,575.19 1,378,116.05 2. a. Extra Work 430,998.75 14,200.08 b. Adustment Comp. 3. Materials on Hand 108,543.55 -21,316.31 4. Earned Subject to Retention 22,193,117.49 1,370,999.82 5. Mobilization 829,350.00 0.00 6. Total Work Completed 22,913,923.94 7. Deductions -62,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,960,467.49 1,360,999.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,360,999.82