Dept. of Trans. PROGRESS Serial No. Contract No. 19-358-10-03 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 59% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 017 Payment period ending: 12-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,077,664.82 1,042,137.28 2. a. Extra Work 767,749.07 279,033.30 b. Adustment Comp. 3. Materials on Hand 108,543.55 0.00 4. Earned Subject to Retention 25,953,957.44 1,321,170.58 5. Mobilization 829,350.00 0.00 6. Total Work Completed 26,674,763.89 7. Deductions -5,000.00 57,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,778,307.44 1,378,170.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,378,170.58