Dept. of Trans. PROGRESS Serial No. Contract No. 20-022-13-29 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 63% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 018 Payment period ending: 01-20-20 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,637,661.08 559,996.26 2. a. Extra Work 771,730.10 3,981.03 b. Adustment Comp. 3. Materials on Hand 108,543.55 0.00 4. Earned Subject to Retention 26,517,934.73 563,977.29 5. Mobilization 829,350.00 0.00 6. Total Work Completed 27,238,741.18 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,342,284.73 563,977.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 563,977.29