Dept. of Trans. PROGRESS Serial No. Contract No. 20-118-08-34 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 72% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 021 Payment period ending: 04-20-20 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,600,397.46 90,238.33 2. a. Extra Work 1,229,318.56 268,396.82 b. Adustment Comp. 3. Materials on Hand 103,587.35 -4,956.20 4. Earned Subject to Retention 27,933,303.37 353,678.95 5. Mobilization 829,350.00 0.00 6. Total Work Completed 28,659,066.02 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,762,653.37 353,678.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 353,678.95