Dept. of Trans. PROGRESS Serial No. Contract No. 20-206-16-35 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 86% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 024 Payment period ending: 07-20-20 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,257,697.08 174,202.88 2. a. Extra Work 1,867,594.65 372,735.47 b. Adustment Comp. -130,107.74 -130,107.74 3. Materials on Hand 4. Earned Subject to Retention 29,995,183.99 416,830.61 5. Mobilization 829,350.00 0.00 6. Total Work Completed 30,824,533.99 7. Deductions -2,000.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,822,533.99 419,830.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 419,830.61