Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-155-17-16 07-3009U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-110-0.7/24.1 ACIM-110-1(841) Progress payment No. 034 Payment period ending: 04-21-21 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,035,627.56 88,466.80 2. a. Extra Work 2,953,784.70 0.00 b. Adustment Comp. -118,755.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 31,870,656.52 88,466.80 5. Mobilization 829,350.00 0.00 6. Total Work Completed 32,700,006.52 7. Deductions 0.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,700,006.52 93,466.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 93,466.80