Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-12-07 07-301104 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 26% Location: Federal Project: 07-LA-60-R2.8/11.8 ACNH-X037(211) 07-LA-710-24.1/25.1 Progress payment No. 015 Payment period ending: 11-20-20 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,040,511.28 5,968,512.96 2. a. Extra Work 11,394,763.60 1,136,715.09 b. Adustment Comp. 135,369.71 9,773.20 3. Materials on Hand 711,636.17 -123,321.74 4. Earned Subject to Retention 65,282,280.76 6,991,679.51 5. Mobilization 10,407,447.00 0.00 6. Total Work Completed 74,978,091.59 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 75,686,727.76 6,988,679.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,988,679.51