Dept. of Trans. PROGRESS Serial No. Contract No. 21-356-14-56 07-301104 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 42% Location: Federal Project: 07-LA-60-R2.8/11.8 ACNH-X037(211) 07-LA-710-24.1/25.1 Progress payment No. 028 Payment period ending: 12-20-21 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 82,172,611.98 220,757.00 2. a. Extra Work 19,331,687.33 624,232.76 b. Adustment Comp. 1,106,022.12 -405,565.25 3. Materials on Hand 4. Earned Subject to Retention 102,610,321.43 439,424.51 5. Mobilization 10,407,447.00 0.00 6. Total Work Completed 113,017,768.43 7. Deductions 0.00 15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 113,017,768.43 454,424.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 454,424.51